House eight

FTLComm - Tisdale - Thursday, May 28, 2009

With is west wall in place this new house is well on its way to becoming a structure. This (above) is how it looked at 2:24 this afternoon.

Work began on this site at the end of the new cul-de-sac on May 4th when Lebel Trenching of Zenon Park dug in the basement area for the footings and water and sewer lines.

This was the second project to get underway with the first project having begun just a few days earlier on the lot just north of this one. That project has advanced pretty much at the same speed but was not the first to get a wall up.

 
 

I am not quite sure what happened here but on May 7th (above) the town spent the day moving the fire hydrant that was in front of this new project. Hard to tell from my perspective as to why it had to be moved all that is clear is that it took a little more then a days work to move the hydrant and water service.

Like the house beside it this new house has a wood basement with "i" beam floor jost which were put in place on May 22nd.

This is a nice site and will have a big back yard but the street seems a bit tight the way it is laid out.

 
 
Timothy W. Shire
 

Return to Ensign

 
This page is a story posted on Ensign, a daily web site offering a variety of material from scenic images, political commentary, information and news. This publication is the work of Faster Than Light Communications . If you would like to comment on this story or you wish to contact the editor of these sites please send us email.
 

Editor : Timothy W. Shire
Faster Than Light Communication
Box 1776, Tisdale, Saskatchewan, Canada, S0E 1T0
306 873 2004