most of the walls for the first floor of the Canalta motel were standing at 2:07 this afternoon
|
|||||
Canalta gets its first floor walls |
|||||
FTLComm - Tisdale - Monday, December 21, 2009 | |||||
We showed you some of this project's beginnings on October 22nd and since then the project has been grinding along. We begin this episode on November 3rd as Chupa Excavation and Trucking looked after the installation of the water and sewer sevices. At this point the whole site had been prepared for construction as the surface material was taken away and a solid base of compressed gravel was put in place. Below on November 5th the sevices excavation was backfilled and packed down. |
|||||
This the scene (right), was at 2:13 on November 17th as piles were drilled and poured to provide a solid base for the foundation to come. |
|||||
This picture (right) was taken the next day at 4:00 in the afternoon and you can see the work of trying to keep the damp forms warm. The image below shows the first steel being erected on the site. This is how things looked at 1:00 in the afternoon of December 17th. That arctic air was brutal during this part of the process and it is surprising to see the progress that had been made. At this point the lumber and floor trusses were piled up on the site and the work force tripled. |
|||||
At 2:00 this afternoon the east and south sides of the first floor were in place with the floor trusses for the second floor being installed. |
|||||
|